Post Tsunami Recovery and Reconstruction Project
Sub-Component 1: School Upgrading (World Bank & Government)
Updated: 3 June 2008
             
# Atoll / Island  School Scope of Work Total  (USD) Status % Completed
1 H.Dh. Kulhudhuffushi Hdh.Afeefuddin School Hall (1 Hall, 1 Common room) 357,728.92 Foundation laid by Minister Zahiya on 10/10/2006. Project awarded. Sight hand overed on 4-4-2007. Foundation cheked on 11-06-2007. Site supervisor appointed Mohamed Ali Lido 18-06-2007. requested school to send copy of agreement on 18-06-2007. Requested contractor to build a fence around the construction site (02/7/2007). Roof work on going.(13-11-2007). Back filling works ongoing. 70%
2 H.Dh. Naivaadhoo HDh.Naivaadhoo School 3 classroom 80,996.08 Project Construction works Completed. Final Inspection done and retention held 100%
3 H.Dh. Nellaidhoo HDh.Nellaidhoo School 3 classroom 80,996.08 Project Construction works Completed. Final Inspection done and retention held 100%
4 Sh. Maroshi Sh.Madhurasathul Munavvara Toilet block, boundary wall 39,796.08 Project Stopped 0%
5 Sh. Komandoo Sh.Atoll Education Centre Hall (1 Hall, 1 Common room), 4 classroom 466,410.78 Project Designing & Drawing Completed. Project Retendered & Awarded. Contract signed on 16-09-2007. Fence works (65000/-) & Site cleaning works (55000/-) approved on 5-11-2007.Ground works and Foundation works finished.foundation checked on 13-11-2007. Catwork slab checked on 12-02-2008 20%
6 N. Kudafari N. Kudafari School 3 classroom, toilet block 90,457.65 Project Construction works Completed. Final Inspection done and retention held. Send practical completion report to Contractor. 100%
7 N. Maafaru N. Maafaru  School 3 classroom 80,229.41 Project Construction works Completed. Final Inspection done and retention held. Send practical completion report to Contractor. 100%
8 R. Alifushi  R. Alifushi School 4 classroom, library, 2 labs, store room, toilet block 361,960.78 Project Designing & Drawing Completed. Project awarded. Contract signined and sight hand overed. Requseted school to find a temoporary site supervisor and inform MOE (31-05-2007). Foundation checked on 18-7-2007. Site supervisor appointed 5-9-2007. First floor slab checked. Concrete works ongoing. Ceiling work ongoing. 70%
9 R. Hulhudhuffaaru R. Hulhudhuffaaru School 3 classroom, 2 labs, library, Store room, toilet block 234,156.86 Project Designing & Drawing Completed. Project awarded. Contract signined and sight hand overed. Requseted school to find a temoporary site supervisor and inform MOE (31-05-2007). Foundation checked on 25-6-2007.  First floor slab checked. Concrete works ongoing.Roof work ongoing.(13-11-2007). Electrical wiring and back filling works ongoing 95%
10 B. Kendhoo B. Kendhoo  School 4 classroom  106,972.55 Construction works Completed. Final inspection done and retention held 100%
11 B. Kihaadhoo  B. Kihaadhoo  School Boundary Wall 30,901.96 Construction works Completed. Final inspection done and retention held 100%
12 B. Goidhoo  B. Goidhoo School 4 classroom, toilet block 124,786.27 Construction works Completed. Final inspection done and retention held. World bank mission visited the school on 18-01-2007. Retention period completed 19-2-2008 100%
13 Lh. Hinnavaru Lh. Hinnavaru School Hall (1 Hall, 1 Common room) 272,713.73 Project Designing & Drawing Completed. Project is Awarded . Requested contractor to submit infor about sight Engineer, supervisor & Labours and the schedule. Approved 80,000/- for demolition of old Headmaster house & boundary wall 3-05-2007. Site supervisor selected from the island 03-07-2007.  Found-ation checked. Concrete works ongoing. MUE TRIP 18-11-07. Roofing works ongoing. 70%
14 K. Gaafaru K. Gaafaru School 2 classroom, boundary wall 88,256.86 Construction works Completed. Final inspection done and retention held. Retention period completed 19-2-2008 100%
15 K. Gulhi K. Gulhi School 2 classroom 55,019.61 Construction works Completed. Final inspection done and retention held 100%
16 K. Himmafushi  K. Himmafushi School 3 classroom 80,996.08 Construction works Completed. Final inspection done and retention held 100%
17 A.A. Bodu Folhudhoo  A.A. Bodu Folhudhoo School 3 classroom, toilet block 96,058.82 Construction works Completed. Final inspection done and retention held. Retention period completed 19-2-2008 100%
18 A.A. Himandhoo A.A. Himandhoo School 3 classroom 80,229.41 Project Construction works Completed. Final Inspection to be done. Final inspection was not done as all finishing works are not completed and informed the contractor that and to complete all the works. School Informed that all works completed on 8-2-2007 99%
19 A.A. Mathiveri  A.A.Mathiveri School 3 classroom 80,229.41 Construction works Completed. Final inspection done and retention held. Retention period completed 19-2-2008 100%
20 A.Dh. Kun'burudhoo A.Dh. Kun'burudhoo School 3 classroom 80,229.41 Construction works Completed. Final inspection done and retention held 100%
21 A.Dh. Maamigili  A.Dh.Atoll School 3 classroom 80,229.41 Construction works Completed. Final inspection done and retention held 100%
22 M. Kolhufushi   M. Kolhufushi School Boundary Wall 30,235.29 Construction works Completed. Final inspection done and retention held 100%
23 M. Dhiggaru  M. Dhiggaru School 4Classroom hall 106,205.88 Construction works Completed. Final inspection done and retention held 100%
24 M. Maduvvari  M. Maduvvari School 3 classroom, boundary wall 113,466.67 Construction works Completed. Final inspection done and retention held 100%
25 M. Muli  M. Atoll Education Centre 3 classroom, library, room, toilet block, admin area 299,115.29 Project stopped and fund reallocated. Project changed to Europion Unioin grant. 0%
26 F. Magoodhoo F. Magoodhoo School 2 classroom, boundary wall 89,023.53 Construction works Completed. Final inspection done and retention held 100%
27 Dh. Hulhudheli Dh. Hulhudheli School 2 classroom 54,252.94 Construction works Completed. Final inspection done and retention held 100%
28 Dh. Maen'boodhoo  Dh.Maen'boodhoo School 2 classroom 54,252.94 Construction works Completed. Final inspection done and retention held. Retention period completed 19-2-2008 100%
29 Th. Kin'bidhoo Th. Kin'bidhoo School 2 classroom, boundary wall 72,021.57 Project is Awarded & Contract signed. Requested to inform that the contractor can do extra works (floor tiles for 2 classrooms) for 20000/- on 29-01-2007. boundary wall works ongoing. Colour scheme appoved on 28-05-2007. Finishing works ongoing.to be done the final inspection. 99%
30 Th. Omadhoo Th. Omadhoo School 2 classroom 54,252.94 Project Construction works Completed. Final Inspaction to be done. Retention period completed 19-2-2008 99%
31 Th. Madifushi  Th. Madifushi School Boundary Wall 28,941.18 Construction works Completed. Final inspection done and retention held 100%
32 L. Fonadhoo  L. Atoll Education Centre Hall (1 Hall, 1 Library, 1 Common room) 295,134.31 Project Designing & Drawing Completed. Requested to Re-tender the Project as the prices are too high.(11-3-07). Foundation laid by Deputy  Minister  Hussain on 7-05-2007. Project awarded. Requseted school to find a temoporary site supervisor and inform MOE (31-10-2007). foundation cheked on 4-11-2007. roof beam cheked on 28-12-2007. Requested to submit qotation for some extra works on 13-1-2008. Roof beam checked on 08-02-2008 35%
33 L. Isdhoo L. Isdhoo School 3 classroom 80,996.08 Construction works Completed. Final inspection done and retention held 100%
34 L. Isdhoo-Kalaidhoo L. Isdhoo-Kalaidhoo  School 2 classroom 55,019.61 Construction works Completed. Final inspection done and retention held 100%
35 L. Maabaidhoo L. Maabaidhoo  School 2 classroom 54,252.94 Construction works Completed. Final inspection done and retention held 100%
36 G.A. Dhaandhoo G.A. Dhaandhoo School 6 classroom (1 Staff room, 1Computer room, 1Library,1 Science room, 1 Toilet Block) 159,692.16 Project Designing & Drawing Completed. Project awarded. Requseted school to find a temporary site supervisor and inform MOE (03-06-2007). Sight handovered on 09-06-2007. Contract signed.informed school that MOE can give 20000/- for compensation of citizens water tanks in extended land to school. 31-07-2007. approoved to give 4700/- for conpensation for the trees in extended land 06-08-2007. First sheet Slab checked on 6-11-2007. Roofing work ongoing. Hand Railing estimate (28362.00) aproved on 19-2-2008. 60%
37 G.A. Nilandhoo G.A. Nilandhoo School 2 classroom 54,252.94 Construction works Completed. Final inspection done and retention held. Retention period completed 19-2-2008 100%
38 G.A. Gemanafushi  G.A. Gemanafushi School 3 classroom, boundary wall 87,490.20 Construction works Completed. Final inspection done and retention held 100%
39 G.Dh. Rathafandhoo G.Dh. Rathafandhoo School 3 classroom, boundary wall 86,723.53 Project Construction works Completed. Final Inspection to be done.  99%
40 G.Dh. Vaadhoo G.Dh. Vaadhoo School 3 classroom, boundary wall 86,723.53 Construction works Completed. Final inspection done and retention held 100%
Source : MOE
Total Projects                       40
O Projects Ongoing (O)                       10
C Projects Completed ( C )                       28
S Projects Stoped (S)                         2