| Post
Tsunami Recovery and Reconstruction Project |
|
|
|
| Sub-Component 1:
School Upgrading (World Bank & Government) |
|
|
|
|
|
Updated: 3 June 2008 |
| |
|
|
|
|
|
|
| # |
Atoll / Island |
School |
Scope of Work |
Total (USD) |
Status |
%
Completed |
| 1 |
H.Dh. Kulhudhuffushi |
Hdh.Afeefuddin School |
Hall (1 Hall, 1
Common room) |
357,728.92 |
Foundation
laid by Minister Zahiya on 10/10/2006. Project awarded. Sight hand overed on
4-4-2007. Foundation cheked on 11-06-2007. Site supervisor appointed Mohamed
Ali Lido 18-06-2007. requested school to send copy of agreement on
18-06-2007. Requested contractor to build a fence around the construction
site (02/7/2007). Roof work on going.(13-11-2007). Back filling works
ongoing. |
70% |
| 2 |
H.Dh. Naivaadhoo |
HDh.Naivaadhoo School |
3 classroom |
80,996.08 |
Project
Construction works Completed. Final Inspection done and retention held |
100% |
| 3 |
H.Dh. Nellaidhoo |
HDh.Nellaidhoo School |
3 classroom |
80,996.08 |
Project
Construction works Completed. Final Inspection done and retention held |
100% |
| 4 |
Sh. Maroshi |
Sh.Madhurasathul
Munavvara |
Toilet block,
boundary wall |
39,796.08 |
Project
Stopped |
0% |
| 5 |
Sh. Komandoo |
Sh.Atoll Education
Centre |
Hall (1 Hall, 1
Common room), 4 classroom |
466,410.78 |
Project
Designing & Drawing Completed. Project Retendered & Awarded. Contract
signed on 16-09-2007. Fence works (65000/-) & Site cleaning works
(55000/-) approved on 5-11-2007.Ground works and Foundation works
finished.foundation checked on 13-11-2007. Catwork slab checked on 12-02-2008 |
20% |
| 6 |
N. Kudafari |
N. Kudafari School |
3 classroom, toilet
block |
90,457.65 |
Project
Construction works Completed. Final Inspection done and retention held. Send
practical completion report to Contractor. |
100% |
| 7 |
N. Maafaru |
N. Maafaru School |
3 classroom |
80,229.41 |
Project
Construction works Completed. Final Inspection done and retention held. Send
practical completion report to Contractor. |
100% |
| 8 |
R.
Alifushi |
R. Alifushi School |
4
classroom, library, 2 labs, store room, toilet block |
361,960.78 |
Project
Designing & Drawing Completed. Project awarded. Contract signined and
sight hand overed. Requseted school to find a temoporary site supervisor and
inform MOE (31-05-2007). Foundation checked on 18-7-2007. Site supervisor
appointed 5-9-2007. First floor slab checked. Concrete works ongoing. Ceiling
work ongoing. |
70% |
| 9 |
R. Hulhudhuffaaru |
R. Hulhudhuffaaru
School |
3
classroom, 2 labs, library, Store room, toilet block |
234,156.86 |
Project
Designing & Drawing Completed. Project awarded. Contract signined and
sight hand overed. Requseted school to find a temoporary site supervisor and
inform MOE (31-05-2007). Foundation checked on 25-6-2007. First floor slab checked. Concrete works
ongoing.Roof work ongoing.(13-11-2007). Electrical wiring and back filling
works ongoing |
95% |
| 10 |
B. Kendhoo |
B. Kendhoo School |
4
classroom |
106,972.55 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 11 |
B.
Kihaadhoo |
B. Kihaadhoo School |
Boundary Wall |
30,901.96 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 12 |
B.
Goidhoo |
B. Goidhoo School |
4 classroom, toilet
block |
124,786.27 |
Construction
works Completed. Final inspection done and retention held. World bank mission
visited the school on 18-01-2007. Retention period completed 19-2-2008 |
100% |
| 13 |
Lh. Hinnavaru |
Lh. Hinnavaru School |
Hall (1 Hall, 1
Common room) |
272,713.73 |
Project
Designing & Drawing Completed. Project is Awarded . Requested contractor
to submit infor about sight Engineer, supervisor & Labours and the
schedule. Approved 80,000/- for demolition of old Headmaster house &
boundary wall 3-05-2007. Site supervisor selected from the island
03-07-2007. Found-ation checked.
Concrete works ongoing. MUE TRIP 18-11-07. Roofing works ongoing. |
70% |
| 14 |
K. Gaafaru |
K. Gaafaru School |
2 classroom, boundary
wall |
88,256.86 |
Construction
works Completed. Final inspection done and retention held. Retention period
completed 19-2-2008 |
100% |
| 15 |
K. Gulhi |
K. Gulhi School |
2 classroom |
55,019.61 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 16 |
K.
Himmafushi |
K. Himmafushi School |
3 classroom |
80,996.08 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 17 |
A.A. Bodu Folhudhoo |
A.A. Bodu Folhudhoo
School |
3 classroom, toilet
block |
96,058.82 |
Construction
works Completed. Final inspection done and retention held. Retention period
completed 19-2-2008 |
100% |
| 18 |
A.A. Himandhoo |
A.A. Himandhoo School |
3 classroom |
80,229.41 |
Project
Construction works Completed. Final Inspection to be done. Final inspection
was not done as all finishing works are not completed and informed the
contractor that and to complete all the works. School Informed that all works
completed on 8-2-2007 |
99% |
| 19 |
A.A. Mathiveri |
A.A.Mathiveri School |
3 classroom |
80,229.41 |
Construction
works Completed. Final inspection done and retention held. Retention period
completed 19-2-2008 |
100% |
| 20 |
A.Dh. Kun'burudhoo |
A.Dh. Kun'burudhoo
School |
3 classroom |
80,229.41 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 21 |
A.Dh. Maamigili |
A.Dh.Atoll School |
3 classroom |
80,229.41 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 22 |
M. Kolhufushi |
M. Kolhufushi School |
Boundary Wall |
30,235.29 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 23 |
M.
Dhiggaru |
M. Dhiggaru School |
4Classroom hall |
106,205.88 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 24 |
M.
Maduvvari |
M. Maduvvari School |
3
classroom, boundary wall |
113,466.67 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 25 |
M.
Muli |
M. Atoll Education
Centre |
3
classroom, library, room, toilet block, admin area |
299,115.29 |
Project
stopped and fund reallocated. Project changed to Europion Unioin grant. |
0% |
| 26 |
F. Magoodhoo |
F. Magoodhoo School |
2
classroom, boundary wall |
89,023.53 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 27 |
Dh. Hulhudheli |
Dh. Hulhudheli School |
2
classroom |
54,252.94 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 28 |
Dh. Maen'boodhoo |
Dh.Maen'boodhoo
School |
2
classroom |
54,252.94 |
Construction
works Completed. Final inspection done and retention held. Retention period
completed 19-2-2008 |
100% |
| 29 |
Th. Kin'bidhoo |
Th. Kin'bidhoo School |
2
classroom, boundary wall |
72,021.57 |
Project
is Awarded & Contract signed. Requested to inform that the contractor can
do extra works (floor tiles for 2 classrooms) for 20000/- on 29-01-2007.
boundary wall works ongoing. Colour scheme appoved on 28-05-2007. Finishing
works ongoing.to be done the final inspection. |
99% |
| 30 |
Th. Omadhoo |
Th. Omadhoo School |
2
classroom |
54,252.94 |
Project
Construction works Completed. Final Inspaction to be done. Retention period
completed 19-2-2008 |
99% |
| 31 |
Th.
Madifushi |
Th. Madifushi School |
Boundary
Wall |
28,941.18 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 32 |
L.
Fonadhoo |
L. Atoll Education
Centre |
Hall
(1 Hall, 1 Library, 1 Common room) |
295,134.31 |
Project
Designing & Drawing Completed. Requested to Re-tender the Project as the
prices are too high.(11-3-07). Foundation laid by Deputy Minister
Hussain on 7-05-2007. Project awarded. Requseted school to find a
temoporary site supervisor and inform MOE (31-10-2007). foundation cheked on
4-11-2007. roof beam cheked on 28-12-2007. Requested to submit qotation for
some extra works on 13-1-2008. Roof beam checked on 08-02-2008 |
35% |
| 33 |
L. Isdhoo |
L. Isdhoo School |
3
classroom |
80,996.08 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 34 |
L. Isdhoo-Kalaidhoo |
L.
Isdhoo-Kalaidhoo School |
2
classroom |
55,019.61 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 35 |
L. Maabaidhoo |
L. Maabaidhoo School |
2
classroom |
54,252.94 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 36 |
G.A. Dhaandhoo |
G.A. Dhaandhoo School |
6
classroom (1 Staff room, 1Computer room, 1Library,1 Science room, 1 Toilet
Block) |
159,692.16 |
Project
Designing & Drawing Completed. Project awarded. Requseted school to find
a temporary site supervisor and inform MOE (03-06-2007). Sight handovered on
09-06-2007. Contract signed.informed school that MOE can give 20000/- for
compensation of citizens water tanks in extended land to school. 31-07-2007.
approoved to give 4700/- for conpensation for the trees in extended land
06-08-2007. First sheet Slab checked on 6-11-2007. Roofing work ongoing. Hand
Railing estimate (28362.00) aproved on 19-2-2008. |
60% |
| 37 |
G.A. Nilandhoo |
G.A. Nilandhoo School |
2
classroom |
54,252.94 |
Construction
works Completed. Final inspection done and retention held. Retention period
completed 19-2-2008 |
100% |
| 38 |
G.A. Gemanafushi |
G.A. Gemanafushi
School |
3
classroom, boundary wall |
87,490.20 |
Construction
works Completed. Final inspection done and retention held |
100% |
| 39 |
G.Dh. Rathafandhoo |
G.Dh. Rathafandhoo
School |
3 classroom, boundary
wall |
86,723.53 |
Project
Construction works Completed. Final Inspection to be done. |
99% |
| 40 |
G.Dh. Vaadhoo |
G.Dh. Vaadhoo School |
3 classroom, boundary
wall |
86,723.53 |
Construction
works Completed. Final inspection done and retention held |
100% |
| Source
: MOE |
|
|
|
|
|
|
|
|
|
|
|
|
|
Total Projects |
40 |
|
O |
Projects Ongoing (O) |
10 |
|
C |
Projects Completed ( C ) |
28 |
|
S |
Projects Stoped (S) |
2 |
|
|
|
|
|
|
|
|
|